Deadlines and requirements you should know about

Tags

The Prescriptive Pathway is one of the three Principal Compliance Pathways. This Pathway is available for all Property Types. It is an action-based compliance method that includes reporting milestones and implementing one or more recommended energy efficiency measures (EEMs) designed to achieve energy savings (a minimum Site EUI reduction of 20%) comparable to the Performance Pathway. Compliance under the Prescriptive Pathway is met by successfully completing specific actions and meeting reporting/verification requirements.

This Pathway is designed to help building owners mitigate risk for a Compliance Cycle—so long as they successfully implement the specific approved EEMs and meet all reporting/verification requirements, the building will comply, regardless of its measured energy performance. Because the Prescriptive Pathway is action-based and does not rely on a performance evaluation at the end of the Cycle, the selection of evaluation year(s) does not apply to this Pathway.

Important deadlines and requirements

Timeline Key

Major BEPS Cycle Milestone

Phase

Deadline or Deliverable

Milestone: BEPS 1 Begins

DOEE established the first set of BEPS on January 1, 2021, thus beginning the BEPS 1 Compliance Cycle.

Phase 1 Begins

January 1, 2021 – April 1, 2023

Pathway Selection and Energy Audit

Benchmarking Report Due

A completed District Benchmarking Benchmark Results and Compliance Report is due for buildings ≥25,000 sq. ft. for calendar year 2021.

Phase 1 Deliverables

Submit Pathway Selection and Energy Audit

Deadline to submit the Pathway Selection Form to DOEE for approval by telling them you’ve selected the Prescriptive Pathway. You must also include an Energy Audit that meets the requirements outlined by DOEE.

Phase 2 Begins

End of Phase 1 – April 1, 2024

Action Plan

Note: Phase 2 may begin as soon as Phase 1 is complete.

Benchmarking Report Due

A completed District Benchmark Results and Compliance Benchmarking Report is due for buildings ≥25,000 sq. ft. for calendar year 2022.

Phase 2 Deliverables

Submit Action Plan

Deadline to submit an O&M Program and Action Plan with a Final EEM Package to implement in Phase 3.

Phase 3 Begins

End of Phase 2 – April 1, 2026

Implementation

Note: Phase 3 may begin as soon as Phase 2 is complete.

Third-Party Verified Benchmarking Report Due

A completed, third-party verified District Benchmark Results and Compliance Benchmarking Report is due for buildings ≥25,000 sq. ft. for calendar year 2023.

Benchmarking Report Due

A completed District Benchmark Results and Compliance Benchmarking Report is due for buildings ≥10,000 sq. ft. for calendar year 2024.

Phase 3 Deliverables

Submit Implementation Report

Deadline to submit your Implementation Report, including 1) an Implementation Verification with supporting documentation to verify the EEMs were installed as approved, and 2) an attestation of implementation of the approved O&M program.

Phase 4 Begins

End of Phase 3 – April 1, 2027

Evaluation, Monitoring, and Verification

Note: Phase 4 may begin as soon as Phase 3 is complete.

Benchmarking Report Due

A completed District Benchmark Results and Compliance Benchmarking Report is due for buildings ≥10,000 sq. ft. for calendar year 2025.

Milestone: Compliance Cycle 1 Ends

This is the end of the BEPS 1 Compliance Cycle.

Phase 4 Deliverables

Submit Evaluation, Monitoring, and Verification Report

Deadline to submit an Evaluation, Monitoring, and Verification Report including, 1) Post-implementation Analysis, 2) Unfinished Phase 3 Verification, and 3) Updated O&M Program and Attestation.